Joint transformation programme update

Decision Maker: Eastbourne Borough Council Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Report will provide an update on the joint transformation programme. In October 2015, cabinet approved a strategy for the development of shared services between Lewes District Council and Eastbourne Borough Council based on the integration of the majority of council services.

Decision:

(Key decision):

 

(1) To note the progress of the joint transformation programme.

 

(2) To approve the business case for the joint transformation programme phase 3 which included recommendations to approve:

 

(a)  The total savings/income target of £400,000 for phase 3.

 

(b)  The approach for delivering the phase 3 transformation and savings/income.

 

(c)  The phase 3 governance arrangements.

 

(d)  The phase 3 costs and allocate an additional £1.4m to the programme (£700,000 from Eastbourne Borough Council).

 

(e)  The revised costs and benefits realisation ratio of 50:50 between Eastbourne Borough and Lewes District Councils.

Report author: Lee Banner

Publication date: 25/10/2018

Date of decision: 24/10/2018

Decided at meeting: 24/10/2018 - Eastbourne Borough Council Cabinet

Effective from: 02/11/2018