Meeting: 11/09/2019 - Eastbourne Borough Council Cabinet (Item 28)

28 Sovereign Energy Centre pdf icon PDF 64 KB

Report of Director of Regeneration and Planning

Lead Cabinet member: Councillor Jonathan Dow

Decision:

(Key decision):

 

To agree a budget of up to £115k to carry out additional feasibility and design work for a stand alone energy centre at the Sovereign Centre site; this could potentially provide low carbon heat sourced from the embedded energy in the nearby sewer network. If viable, a decision to invest will be considered at the February 2020 Cabinet.

Minutes:

The Cabinet considered the report of the Director of Regeneration and Planning seeking approval to progress a renewable energy centre at the Sovereign Centre site.

 

Resolved (Key decision):

 

To agree a budget of up to £115k to carry out additional feasibility and design work for a stand alone energy centre at the Sovereign Centre site; this could potentially provide low carbon heat sourced from the embedded energy in the nearby sewer network. If viable, a decision to invest would be considered at the February 2020 Cabinet.

 

Reason for decision:

 

To invest in solutions that will reduce the town’s overall carbon footprint whilst also enabling an income generation.