Seafront Lighting Repairs and Replacement

17/03/2020 - Seafront Lighting Reinstatement

(Key decision):

 

(1) To agree that funds up to the level already earmarked for the project within the Council’s capital programme be released to support seafront lighting reinstatement works

 

(2) To agree a waiver of the Council’s Contract Procedure Rules for necessary works in connection with reinstatement of the lighting and award the contract for works to the Council’s term electrical contractor, GM Monk;

 

(3) To authorise the Accountable Officer to sign a waiver of the Council’s Contract Procedure Rules to GM Monk in connection with these works.