(Key decision):
(1) To approve an increase in the General Fund Capital Programme budget for the scheme from £2.2m to £2.9m, with the additional £700,000 to be funded from Right to Buy Receipts.
(2) To report an amendment to a waiver previously approved to the Contract Procurement Rules (CPR), as set out in paragraph. 2.4.1(a) of CPR to allow the direct selection of a main contractor, due to the bespoke nature of the product required and time restrictions.