Millie McDevitt, Performance
and Management Lead, introduced the report which provided detail of
the Council’s performance in Quarter 1 2019/20 (1 April
– 30 June 2019). During discussion the following points were
highlighted:
Target completion dates for
Council projects – the Committee sought clarification on a
number of completion dates for projects included in the
Regeneration and Business, and the Finance and Corporate Projects
and Programmes sections of the report. Officers agreed to discuss
the issue with the relevant project managers and where available to
provide detail on interim milestones/dates and on the status of
those projects.
Calls to the
Contact Centre – Officers advised
Members that during quarter 1 the volume of calls to the Contact
Centre had increased significantly, generated predominantly through
the issuing of council tax, business rate bills and election
related enquiries. There had also been two elections in May
(European and local elections). The performance indicators for this
area were under review and would in the future look at the quality
of the call response as well as the speed of the response. Members
suggested that the volume of calls answered during peak times be
analysed.
Homes First
presentation – Simon Watts, Interim
Lead, Homes First Property Services, updated the Committee on the
work being undertaken towards managing void properties and re-let
times ‘Key to Key’. During discussion the following
points were highlighted:
- The charge-back
process allowed the Council to recover costs for voids and all
other day-to-day repairs where tenants caused damage. The Homes
First team was responsible for managing void repairs and Mears
managed day-to-day repairs. Collection rates were currently low and
work was being done towards improving the monitoring of the
process. A sundry debtor’s account would be set-up and
tighter control would be introduced to ensure tenants took more
responsibility for any damage. The main incentive for tenants who
left properties in a poor condition was that, at some point, they
may need to join the property list again. There would also be
opportunities for money orders (through the County Court) to be
included in cases of repossession.
- The void timetable
had been officer led using good practice. The opportunity for
Member input into the timetable would be suggested to the
Council’s Corporate Management Team.
- Each void property
was pre and post inspected and a number of properties were turned
around in five days. However, there were properties requiring
significant refurbishment, modernisation and investment, increasing
the average cost across all void properties. There was not
currently sufficient data across the Council’s stock to
determine the condition of the properties, including the presence
of asbestos, requiring the Council to undertake full refurbishment
and demolition (R&D) surveys. As an organisation, Mears
sub-contracted any work involving asbestos, which extended the
period of re-let time and added to the overall costs. Existing
contracts would be reviewed and where possible value-for-money
would be improved.
- Homes First was using
a new IT system and efforts would be made to look at the void
property spend in previous years, particularly on the individual
elements such as electrics/rewiring, boiler repairs/replacements.
Benchmarking with other organisations (including those that used
Mears) would be undertaken, following the design of the
‘schedule of rates’. This would allow consideration of
different delivery models.
- Lewes District
Council had a capital budget of £4.8 million for housing
repairs (major, planned and cyclical). The response rate of 13000
over 3,000 properties (an average of approximately 4 per property)
did not vary to any great extent from the average. Eighty percent
of the data used to monitor repairs was from a two year old, twenty
percent survey. Newer surveys would be undertaken.
- The Committee
requested that the Homes First Team report back in a year’s
time with an update on the voids/re-letting position.
- The change of
categories for ‘priority need’ within the 2007 Homeless
Reduction Act had contributed to an increase in the numbers of
households in emergency accommodation. There was a work-stream now
ongoing dedicated to reducing the current figure.
Planning
performance – the performance
indicators for planning applications were subject to fluctuation
from quarter to quarter, however, the current targets for major and
minor planning applications had been exceeded. New ways of working,
including new IT systems, would need to be embedded before staff
resources were looked at.
RESOLVED
a) To note the progress and
performance for Quarter 1 as well as the overall
performance for 2019/20;
and
b) Recommend to the Cabinet
that the target dates and interim milestones for Council projects
be reviewed.